Quality mark: From consent to construction

12th April 2019


Web windturbines istock 664541680 1

Related Topics

Related tags

  • Construction ,
  • Planning ,
  • Energy ,
  • Renewable ,
  • Management

Author

Tracy Moffatt

Derek Duckett of Xodus Group gives six top tips to smoothly transition from consent into construction.

There is a hive of activity presently taking place around the upcoming Crown Estate offshore wind leasing rounds throughout the UK, but we should not forget all the good work being undertaken with the projects already in development. In the UK, there is a growing list of offshore wind projects that are either in the early stages of, or working towards, construction and installation. This phase of a project brings with it a different set of tasks and challenges to those encountered during the pre-bid and consenting phases of a project.

Here are six tips to help projects successfully navigate this often-complex path:

  1. Changes to the project design – Ensure your project has a formal design change process, which includes consideration of consenting issues. This will allow identification of any consent implications at the earliest opportunity, including any need for consent variation. Such requirements need to be built into the overall project budget and schedule to avoid showstoppers.
  2. Post consent permits and licences – Generate a permits and licences register and use it to track progress of the applications required, key dates for submission and approval, as well as the relevant authorities that deal with each permit or licence, taking into account regulator review and public consultation periods in the project schedule. Such a register should be kept live, reviewed and updated on a regular basis, and be readily accessible to the key members of the project team.
  3. Managing consent conditions – The management of multi-organisation responsibilities for consent condition compliance is a challenge for every developer. Ensure a suitably resourced post consent and environmental management team who can work out the finer points of condition responsibilities and enshrine an agreement of expectations from all parties involved. For developers, and depending on the scale of the project, a team consisting of a consents manager, an ecological clerk of works (ECoW) who provides advice about ecological and environmental issues during the construction of a development, and an environmental manager supported by project health, safety and environment and engineering teams is recommended to help manage post-consent requirements.
  4. Contractual arrangements – A consents schedule should be an integral part of all contracts with principal contractors and is the key mechanism by which a developer can ensure a project is in compliance with all consent conditions. Principal project contractors are then obligated to cascade relevant conditions to each of their subcontractors through their own contractual processes.
  5. Environmental management documentation – These documents together with the contract schedule provide an agreed method of working throughout the project's life. This documentation will inevitably need to be periodically reviewed to take into account any project or schedule changes. Project specific environmental management plans, which take into account individual project specifications and requirements, help to clarify project expectations at the start of a project and can aid resolution of any subsequent disagreements later in the project.
  6. Training and awareness – Once all environmental management and other consent plans have been agreed, communication of their requirements is needed. This should start with those with specific responsibilities being put through specific project training and/or awareness courses. Those with more general responsibilities should be communicated with through a formal project induction. Specific topics can also be addressed through tool box talks (an informal safety meeting that focuses on specific topics relating to a particular project or task). Lessons learned presentations also provide a good opportunity for training and passing knowledge throughout the workforce.

Much of the above may seem like common sense, however it is the way it is implemented that will help a project successfully comply with its consent conditions, while at the same time reducing the risk of environmental, schedule and financial damages. Early engagement with experienced post-consent and environmental specialists is recommended to assist the management of the post-consents burden for offshore renewables projects.

Derek Duckett is a principal environmental consultant in the EIA Team at Xodus Group, Glasgow

Image credit: iStock

Subscribe

Subscribe to IEMA's newsletters to receive timely articles, expert opinions, event announcements, and much more, directly in your inbox.


Transform articles

UK’s CCUS strategy based on outdated assumptions, government warned

The UK government’s carbon capture, usage and storage (CCUS) strategy is based on optimistic techno-economic assumptions that are now outdated, Carbon Tracker has warned.

13th March 2024

Read more

The UK government’s latest Public Attitudes Tracker has found broad support for efforts to tackle climate change, although there are significant concerns that bills will rise.

13th March 2024

Read more

A consortium including IEMA and the Good Homes Alliance have drafted a letter to UK government ministers expressing disappointment with the proposed Future Homes Standard.

26th February 2024

Read more

Global corporations such as Amazon and Google purchased a record 46 gigawatts (GW) of solar and wind energy last year, according to BloombergNEF (BNEF).

13th February 2024

Read more

Three-quarters of UK adults are concerned about the impact that climate change will have on their bills, according to polling commissioned by Positive Money.

13th February 2024

Read more

The reality of delivering net zero is that we need solutions tailored to specific areas. Peter Gudde explores models that local authorities could adopt

15th January 2024

Read more

Heat pump installations in UK homes increased by nearly a fifth last year, with over 200,000 now having been installed across the country.

11th January 2024

Read more

Last year was the warmest ever recorded, surpassing the previous annual high set in 2016 by a large margin, scientists have confirmed today.

9th January 2024

Read more

Media enquires

Looking for an expert to speak at an event or comment on an item in the news?

Find an expert

IEMA Cookie Notice

Clicking the ‘Accept all’ button means you are accepting analytics and third-party cookies. Our website uses necessary cookies which are required in order to make our website work. In addition to these, we use analytics and third-party cookies to optimise site functionality and give you the best possible experience. To control which cookies are set, click ‘Settings’. To learn more about cookies, how we use them on our website and how to change your cookie settings please view our cookie policy.

Manage cookie settings

Our use of cookies

You can learn more detailed information in our cookie policy.

Some cookies are essential, but non-essential cookies help us to improve the experience on our site by providing insights into how the site is being used. To maintain privacy management, this relies on cookie identifiers. Resetting or deleting your browser cookies will reset these preferences.

Essential cookies

These are cookies that are required for the operation of our website. They include, for example, cookies that enable you to log into secure areas of our website.

Analytics cookies

These cookies allow us to recognise and count the number of visitors to our website and to see how visitors move around our website when they are using it. This helps us to improve the way our website works.

Advertising cookies

These cookies allow us to tailor advertising to you based on your interests. If you do not accept these cookies, you will still see adverts, but these will be more generic.

Save and close