Lucy Whitter, from Peter Brett Associates, discusses the role of environmental impact assessment (EIA) practitioners in applying the principles of the Rochdale Envelope approach

The desire for developers to obtain flexible planning permissions is understandable and often necessary for the viability of schemes. It has led to outline planning consent being sought for maximum and minimum parameters of development in the form of plans and text. This is often accompanied by an illustrative masterplan which indicates one way in which a development can be built out to demonstrate feasibility.

EIA is a mechanism for decision making and must capture all likely significant environmental effects of development, but the use of design parameters presents a particular challenge to this.

Although an illustrative masterplan provides a defined scheme, assessment of its detail in an EIA could result in under-reporting of effects if the scheme is built differently. This is a situation which case law has sort to rectify, specifically the cases of R v Rochdale Metropolitan Borough Council ex parte Tew (1999) and R v Rochdale Metropolitan Borough Council ex parte Milne (2001).

In Tew, the authority consented a scheme with an EIA which assessed an illustrative masterplan. The High Court upheld a challenge to the decision and quashed the planning permission. The description of the scheme was not considered sufficient to enable the main effects of the scheme to be properly assessed, in breach of schedule 4 of the EIA Regulations.

In Milne, the outline permission was restricted so that development could take place only within parameters assessed in the environmental statement. The High Court upheld the authority’s decision to grant planning permission.

The judge emphasised that permissions must be granted in the full knowledge of the likely significant effects on the environment. This doesn’t mean that developers have no flexibility in developing a scheme, but that such flexibility has to be properly assessed and taken into account prior to granting outline planning permission.

In other words, assessing parameters is acceptable and often necessary, but the EIA must assess the significant likely effects resulting from the flexibility of the parameters. This is the approach known as the “Rochdale Envelope”.

So how do we establish the “likely” effects of a flexible scheme?

Although the responsibility for the initial development of parameters often rests with developers and those creating the masterplan, EIA coordinators have a fundamental role to play in ensuring an EIA robustly applies the Rochdale Envelope approach for outline planning applications where appropriate.

EIA coordinators should assist developers and masterplanners to develop parameters that are not so flexible that the likely effects of the scheme cannot be established or so wide as to effectively represent more than one scheme.

EIA coordinators have sometimes interpreted the requirement to assess likely significant effects as authorisation not to assess the worst case scenario. However, the Rochdale Envelope approach is consistent with the idea that maximum adverse effects, if permitted through consent of parameters, need to be established and captured in the assessment.

If parameters do not rule out certain permutations of development, then they should be considered. Otherwise the EIA is open to challenge.

This is not to say that impossible scenarios should be assessed (for example A development exceeding the maximum floor space available), but these should be ruled out within the parameters.

For example, for a mixed use scheme, provision of an overall maximum development quantum allows individual discipline assessors to adjust the balance of the quantum for different land uses, if the parameters allow for different scenarios.

This is applicable for disciplines, such as transport, noise, waste and energy, where the balance of different land use scenarios may result in maximum adverse effects.

EIA coordinators must assist the team in understanding the nature of the parameters and capture maximum adverse effects in assessments.

This may be applicable at several points during the planned construction of the development, as well as to different permutations of the finalised scheme, if the parameters allow for this level of flexibility.

Several scenarios may need to be assessed to establish the maximum adverse effects and therefore more flexible schemes will generally take more time to assess.

However, EIA coordinators can help to design out any adverse effects that may arise from initial review of parameters, reducing the need to fully assess multiple scenarios.

If significant adverse effects are likely to result following development of the scheme in a certain permutation, this should be communicated to the design team early in the process and the parameters narrowed to rule it out if possible.

The importance of mitigation by design through this iterative design process is not a new concept but the Rochdale cases have emphasised a legal basis for EIA team to be fully involved with design of the development parameters right from the beginning.


This article was written as a contribution to the EIA Quality Mark’s commitment to improving EIA practice.

Lucy Whitter is a senior environmental scientist at Peter Brett Associates

Subscribe

Subscribe to IEMA's newsletters to receive timely articles, expert opinions, event announcements, and much more, directly in your inbox.


Transform articles

New guidance maps out journey to digital environmental assessment

IEMA’s Impact Assessment Network is delighted to have published A Roadmap to Digital Environmental Assessment.

2nd April 2024

Read more

Lisa Pool on how IEMA is shaping a sustainable future with impact assessment

27th November 2023

Read more

IEMA responded in September to the UK government’s consultation on the details of the operational reforms it is looking to make to the Nationally Significant Infrastructure Projects (NSIP) consenting process as put forward in the NSIP reform action plan (February 2023).

24th November 2023

Read more

Members of IEMA’s Impact Assessment Network Steering Group have published the 17th edition of the Impact Assessment Outlook Journal, which provides a series of thought pieces on the policy and practice of habitats regulations assessment (HRA).

26th September 2023

Read more

In July, we published the long-awaited update and replacement of one of IEMA’s first published impact assessment guidance documents from 1993, Guidelines for the Environmental Assessment of Road Traffic.

1st August 2023

Read more

Are we losing sight of its intended purpose and what does the future hold for EIA? Jo Beech, Tiziana Bartolini and Jessamy Funnell report.

15th June 2023

Read more

Luke Barrows and Alfie Byron-Grange look at the barriers to adoption of digital environmental impacts assessments

1st June 2023

Read more

Susan Evans and Helen North consider how Environmental Statements can be more accessible and understandable

1st June 2023

Read more

Media enquires

Looking for an expert to speak at an event or comment on an item in the news?

Find an expert

IEMA Cookie Notice

Clicking the ‘Accept all’ button means you are accepting analytics and third-party cookies. Our website uses necessary cookies which are required in order to make our website work. In addition to these, we use analytics and third-party cookies to optimise site functionality and give you the best possible experience. To control which cookies are set, click ‘Settings’. To learn more about cookies, how we use them on our website and how to change your cookie settings please view our cookie policy.

Manage cookie settings

Our use of cookies

You can learn more detailed information in our cookie policy.

Some cookies are essential, but non-essential cookies help us to improve the experience on our site by providing insights into how the site is being used. To maintain privacy management, this relies on cookie identifiers. Resetting or deleting your browser cookies will reset these preferences.

Essential cookies

These are cookies that are required for the operation of our website. They include, for example, cookies that enable you to log into secure areas of our website.

Analytics cookies

These cookies allow us to recognise and count the number of visitors to our website and to see how visitors move around our website when they are using it. This helps us to improve the way our website works.

Advertising cookies

These cookies allow us to tailor advertising to you based on your interests. If you do not accept these cookies, you will still see adverts, but these will be more generic.

Save and close